GG 906 Customer service standard for scheme billboards

(formerly CHE Memo 438/19)

Version 1.0.0

Summary

This document contains requirements for the provision of scheme billboards providing roadwork information to customers.

Application by Overseeing Organisations

Any specific requirements for Overseeing Organisations alternative or supplementary to those given in this document are given in National Application Annexes to this document.

Feedback and Enquiries

Users of this document are encouraged to raise any enquiries and/or provide feedback on the content and usage of this document to the dedicated Highways England team. The email address for all enquiries and feedback is: Standards_Enquiries@highwaysengland.co.uk.

This is a controlled document.

Latest release notes

Document Code Version number Date of publication of relevant change Changes made to Type of change
GG 906 1.0.0 April 2021 Core document, England NAA, Northern Ireland NAA, Scotland NAA, Wales NAA Change to policy, major revision, new document development
GG 906 created for providing scheme roadwork information to customers.

Previous versions

Document Code Version number Date of publication of relevant change Changes made to Type of change

Foreword

Publishing information

This document is published by Highways England.

Contractual and legal considerations

This document forms part of the works specification. It does not purport to include all the necessary provisions of a contract. Users are responsible for applying all appropriate documents applicable to their contract.

Introduction

Background

This is a new document to provide the requirements for the provision of scheme billboards.

Assumptions made in the preparation of this document

The assumptions made in GG 101 [Ref 1.N] apply to this document.

1. Scope

Aspects covered

1.1 The national requirements for the provision of scheme billboards as set out in the National Application Annexes shall be followed.

Implementation 

1.2 This document shall be implemented forthwith on all schemes involving roadworks on the Overseeing Organisations’ motorway and all-purpose trunk roads according to the implementation requirements of  GG 101 [Ref 1.N].

Use of GG 101

1.3 The requirements contained in GG 101 [Ref 1.N] shall be followed in respect of activities covered by this document.

2. Normative references

The following documents, in whole or in part, are normative references for this document and are indispensable for its application. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies.

Ref. Document
Ref 1.N National Highways. GG 101, 'Introduction to the Design Manual for Roads and Bridges'
Skip to content

Design Manual for Roads and Bridges

General Principles & Scheme Governance

General Information

GG 906 England National Application Annex to GG 906 Customer service standard for scheme billboards

(formerly CHE Memo 438/19)

Version 1.0.0

Summary

This National Application Annex sets out the Highways England-specific requirements for scheme billboards providing roadwork information to customers. This document mandates the use of billboards to provide customers travelling through our larger schemes with information on the purpose and duration of the roadworks.

Feedback and Enquiries

Users of this document are encouraged to raise any enquiries and/or provide feedback on the content and usage of this document to the dedicated Highways England team. The email address for all enquiries and feedback is: Standards_Enquiries@highwaysengland.co.uk.

This is a controlled document.

Latest release notes

Document Code Version number Date of publication of relevant change Changes made to Type of change
GG 906 1.0.0 April 2021 England NAA Change to policy, major revision, new document development
Highways England National Application Annex to new GG 906 Customer Service Standard replacing CHE Memo 438/19

Previous versions

Document Code Version number Date of publication of relevant change Changes made to Type of change

Foreword

Publishing information

This document is published by Highways England. It is a new document replacing the provisions of the withdrawn CHE Memo 438/19.

Contractual and legal considerations

This document forms part of the works specification. It does not purport to include all the necessary provisions of a contract. Users are responsible for applying all appropriate documents applicable to their contract.

Introduction

Background

This National Application Annex gives the Highways England-specific requirements related to scheme billboards providing roadwork information to customers.

Highways England, as part of its customer service strategy PR101/15 2016 [Ref 1.I] has introduced customer service standards (CSSs) to challenge management and employees to meet the needs and expectations of our customers. Our customer service strategy identified that our customers want to trust what they are being told, feel in control and have stress-free journeys.

This scheme billboard CSS will encourage best practice and a consistent application of the existing guidance around provision of scheme information to customers as they experience any of Highways England's significant road works.

The document will mandate a consistent application of the provision of scheme information to customers as they travel through road works.

This document will address road user views raised within the Transport Focus report “Incidents and road works. A road user perspective” Incidents and Roadworks [Ref 2.I] which stated: “Road users felt that ‘advance notice’ road works information is important at the roadside, particularly for drivers who use a particular road regularly. Key requirements were felt to be:

  1. start dates and duration;
  2. how I will be affected;
  3. what is being done; and,
  4. how I will benefit.

Billboards do not provide directional information to customers on the motorway and all-purpose trunk road network. Instead they provide information about the roadworks taking place.

This document will also enable Highways England to demonstrate that it is listening and responding to customer concerns, and is now delivering roadworks in a way that better meets its customers' expectations.

Assumptions made in the preparation of this document

The assumptions made in GG 101 [Ref 2.N] apply to this document.

Terms and definitions

Term Definition
Scheme billboard Non-traffic sign displaying information about the road works
Significant scheme Schemes that have a significant impact on customer journeys or are over six months in duration.

E/1. General requirements

Implementation

E/1.1 This document shall be implemented on all significant schemes, as defined in 'Terms and definitions' in this document, on the Highways England motorway and all-purpose trunk roads according to the implementation requirements of DMRB GG 101 [Ref GG 101 [Ref 2.N].

Planning legislation

E/1.2 To comply with the requirements of the Town and Country Planning Act 1990 Part VIII, Chapter III, Section 220 UKPGA 1990/08 [Ref 4.N] express consent must be obtained from the local planning authority prior to installation of scheme billboards.

NOTE Planning advice can be sought by emailing the Highways England Spatial Planning team.

E/1.3 Billboards shall be in addition to the existing contract provision already included in the Manual of Contract Documents for Highway Works (MCHW) as “Information Boards” (Ref. MCHW [Do not use] [Ref 3.N])

Design

E/1.4 Billboards shall communicate the following scheme information:

  1. the benefits to customers;
  2. the nature of the work; and,
  3. the expected completion date.

NOTE Installation of the billboards is outside the scope of this document.

E/1.5 Billboards shall be designed in accordance with Highways England's ' Guidance for our contractors [Ref 1.N].

E/1.6 Contractors shall check the 'Visual Identity' documentation for the most recent design guidance. An example can be found at Appendix E/A.

NOTE Billboards are not subject to the requirements of the Traffic Signs Regulations and General Directions UKSI 2016/362 (TSRGD) [Ref 3.I] and Traffic Signs Manual Chapter 1 TSM Chapter 1 [Ref 4.I].

E/1.7 The billboard design shall be approved by the appropriate regional communications team prior to manufacture and installation.

NOTE 1 Early engagement with regional communications manager and creative team is essential to allow for the use of the most up to date billboard design guidance to be used.

NOTE 2 Appendix E/A.4 provides the suggested approval process for billboards design.

Siting

E/1.8 One billboard shall be located as close as possible to the start of the main scheme traffic management.

E/1.8.1 The need for duplicate billboards should be identified and assessed at all entry points to the scheme where a significant number of customers are joining the scheme, and so not had the opportunity to see the billboard at the start of the scheme.

E/1.8.2 Billboards should not be positioned within the works area.

E/1.9 All billboards shall be visible and legible to customers and not be obstructed by infrastructure or vegetation.

E/1.10 Billboards shall be erected prior to commencement of the scheme.

E/1.10.1 The erection of billboards should be at least four weeks prior to commencement of the scheme.

E/2. Normative references

The following documents, in whole or in part, are normative references for this document and are indispensable for its application. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies.

Ref. Document
Ref 1.N Highways England. Guidance for our contractors, 'Guidance for our contractors'
Ref 2.N National Highways. GG 101, 'Introduction to the Design Manual for Roads and Bridges'
Ref 3.N Highways England. MCHW [Do not use], 'Manual of Contract Documents for Highway Works'
Ref 4.N National Archive. UKPGA 1990/08, 'Town and Country Planning Act'

E/3. Informative references

The following documents are informative references for this document and provide supporting information.

Ref. Document
Ref 1.I Highways England. PR101/15, 'Customer Service Strategy' , 2016
Ref 2.I Transport Focus (Passenger Council). Incidents and Roadworks, 'Incidents and Roadworks - A road user perspective'
Ref 3.I National Archive. UKSI 2016/362 (TSRGD), 'The Traffic Signs Regulations and General Directions'
Ref 4.I TSO. TSM Chapter 1, 'Traffic Signs Manual Chapter 1 - Introduction'

Appendix E/A. Scheme billboard design

E/A1 Billboard design

Figure E/A.1 Colours & images
Figure E/A.2 Approved text options

Figure E/A.3 Units and measures
Figure E/A.4 Approval process for billboard design
Skip to content

Design Manual for Roads and Bridges

General Principles & Scheme Governance

General Information

GG 906 Northern Ireland National Application Annex to GG 906 Customer service standard for scheme billboards

Version 1.0.0

Summary

The requirements of GG 906 do not apply in Northern Ireland.

Feedback and Enquiries

Users of this document are encouraged to raise any enquiries and/or provide feedback on the content and usage of this document to the dedicated team in the Department for Infrastructure, Northern Ireland. The email address for all enquiries and feedback is: dcu@infrastructure-ni.gov.uk

This is a controlled document.

Latest release notes

Document Code Version number Date of publication of relevant change Changes made to Type of change
GG 906 1.0.0 April 2021 Northern Ireland NAA Change to policy, major revision, new document development
Department for Infrastructure Northern Ireland National Application Annex to GG 906

Previous versions

Document Code Version number Date of publication of relevant change Changes made to Type of change
Skip to content

Design Manual for Roads and Bridges

General Principles & Scheme Governance

General Information

GG 906 Scotland National Application Annex to GG 906 Customer service standard for scheme billboards

Version 1.0.0

Summary

The requirements of GG 906 do not apply in Scotland.

Feedback and Enquiries

Users of this document are encouraged to raise any enquiries and/or provide feedback on the content and usage of this document to the dedicated Transport Scotland team. The email address for all enquiries and feedback is: TSStandardsBranch@transport.gov.scot

This is a controlled document.

Latest release notes

Document Code Version number Date of publication of relevant change Changes made to Type of change
GG 906 1.0.0 April 2021 Scotland NAA Change to policy, major revision, new document development
Transport Scotland National Application Annex to GG 906

Previous versions

Document Code Version number Date of publication of relevant change Changes made to Type of change
Skip to content

Design Manual for Roads and Bridges

General Principles & Scheme Governance

General Information

GG 906 Wales National Application Annex to GG 906 Customer service standard for scheme billboards

Version 1.0.0

Summary

The requirements of GG 906 do not apply in Wales.

Feedback and Enquiries

Users of this document are encouraged to raise any enquiries and/or provide feedback on the content and usage of this document to the dedicated Welsh Government team. The email address for all enquiries and feedback is: Standards_Feedback_and_Enquiries@gov.wales

This is a controlled document.

Latest release notes

Document Code Version number Date of publication of relevant change Changes made to Type of change
GG 906 1.0.0 April 2021 Wales NAA Change to policy, major revision, new document development
Welsh Government National Application Annex to GG 906

Previous versions

Document Code Version number Date of publication of relevant change Changes made to Type of change